Update 11-1-2024
Painting is completed up to approximately 790 feet. Crew are currently working up to approximately 820 feet.
Update 9-9-2024
Painting is completed up to 730 feet. Crews are currently working up to 760 feet.
Update 8-26-2024
The Tower has been painted up to approximately 690 feet. Crews are currently working above 690 feet.
Update 7-24-2024
The tower has been painted up to approximately 590 feet. Crews are currently working between 590-645 feet.
Update 6-5-2024
The tower has been painted up to approximately 500 feet. Crews are currently working between 500-590 feet.
Update 5-1-2024
Tower crews finished painting all of the ground based structures between the tower and the three transmitter buildings. The tower has been painted up to approximately 390 feet. Crews are currently working between 390-490 feet.
Update 3-22-2024
The tower crew is finishing the structures near the ground. As weather allows, work will continue on the tower very soon.
Update 1-31-2024
Tower crews have been working on the structures near the ground since the last update. This work continues.
Update 12-20-2023
The tower crews are working between approximately 320-440 feet above ground as weather permits, and working on ground structures at other times. The tower has been painted up to approximately 320 feet.
Update 11-15-2023
Tower crews are currently working between 238-318 feet above the base of the tower.
Update 11-2-2023
Tower crews are currently working between 168 - 238 feet above the base of the tower.
Update 7-5-2023
The bottom 45 feet of the tower has been prepped and painted. The tower crew has received additional components for the containment system and will begin test fitting and installation of the next tower section this week.
Update 6-13-2023
The tower crew is working to assemble the containment system near the base of the tower in order to finalize the function of the system.
Update 5-18-2023
VTS has arrived on site to begin ground work on the containment system framework.
Update 5-9-2023
Consistent with previously described plans, today workers started delivering equipment to be used to support the repainting process. The equipment is custom-designed and fabricated for the tower. Assembly and pilot testing will require at least several weeks of work. We wanted to notify the community that you may observe related activity.
Update 5-5-2023
Baltimore City permit to commence work has now been issued.
Expect to see painting crews from VTS on site in the coming weeks.
Update 4-13-2023
Materials and crews are expected to arrive on site the first week of May, 2023.